Canary Wharf Tower / London                                                                                                                                                            


THE CLIENT:                                                                                                                                                                                                                      Major structural steelwork contractor (main contractor)

THE ISSUES:                                                                                                                                                                                                                      QIC acted for the main contractor in three concurrent matters:

1). The preparation of an extension of time claim against CWCL. 

2). The defence of a claim for delay and disruption from the reinforced concrete sub-contractor.

3). A claim against the insurers of the tower crane supplier following the collapse of a tower crane supplied by them.

THE CHALLENGE FOR QIC: 
The initial brief was to prepare an extension of time claim for the main contractor against CWCL but during the preparation of this there was a collapse of a tower crane supplied by the crane supplier that caused further delay and disruption. 
Consequently the reinforced concrete sub-contractor submitted a detailed delay and disruption claim against the main contractor, part of this claim derived from matters that were the responsibility of CWCL and part the Crane Supplier. The challenge for QIC was therefore to keep the claims against CWCL and the crane supplier moving forward and determining liability respectively for the delays that occurred whilst defending the claim from the reinforced concrete sub-contractor.

QIC ACTIONS:
The QIC team reviewed all site records including steel erection daily “piece count” and crane logs to prepare the main contractors claim submissions. QIC were appointed as both QUANTUM and Planning Experts in the disputes with the sub-contractor and the crane supplier and expert reports were prepared in the case against the crane supplier prior to the dispute being settled on day one of the litigation proceedings. QIC also commissioned a specialist consultant to prepare a CGI presentation of weekly progress (see examples above). 

Following submission of the claims and counter claims QIC attended a number of meetings with both CWCL and the sub-contractor’s experts to negotiate a settlement.

THE RESULT: 
The dispute between the sub-contractor and the main contractor was amicably settled following adjudication and at the same time the main contractor reached a satisfactory settlement with CWCL. The final ispute with the crane supplier was settled as litigation proceedings commenced. 